Precast concrete manufacturer

Turnover-based storage at a precast concrete plant

Storage by turnover, production planning and a loading plan per pickup slot that cut truck waiting time from up to 3 days to zero.

Role
Developer on the team, from analysis to production planning
Period
2020 – April 2021
Stack
  • Laravel
  • React
  • jQuery
  • REST API

In 30 seconds

Problem

Trucks waited up to 3 days to load, and the overhead crane traveled long distances because goods were not placed according to demand.

Solution

We analyzed product turnover with the sales history, and I built the production planning, stock per quadrant and loading plan per pickup slot.

Impact

Waiting time dropped to zero for trucks arriving during their slot, and loading time inside the plant went down considerably.

Key results

waiting time for trucks arriving during their slot
3 days → 0
with stock tracked row by row
128 quadrants

Context

The company manufactured a wide range of construction products: joists, blocks, filler blocks and many more. Production was stored in about 128 quadrants along three internal lanes, similar to supermarket aisles. Customers picked up goods in scheduled slots, and operators loaded the trucks with an overhead crane.

The problem

The problem had two parts. On one side, trucks could wait whole days, sometimes up to three, to be served. On the other, goods were not placed according to demand, so the crane traveled long distances and loading took a long time.

What we did

I was part of the team from the analysis stage.

  • Turnover analysis. Using the sales history in Excel, we ran an ABC classification (Pareto curve): A products, with high turnover, accounted for most pickups; B products had medium turnover and C products, low.
  • Storage by turnover. Each class got its own zone: high-turnover products were stored near the entrance and the main lanes; medium-turnover products in an intermediate area; and low-turnover products in the farthest sectors.
Top view of the plantTrucks enter from the left into three internal lanes. Storage quadrants are ordered by turnover: high turnover near the entrance, medium in the middle area and low in the farthest sectors. An overhead crane runs across the plant on rails.EntranceOverhead crane on railsTruckLane 1TruckLane 2TruckLane 3High turnoverMedium turnoverLow turnover
Top view: three internal lanes, quadrants ordered by turnover from the entrance and an overhead crane on rails. Part of the 128 quadrants is shown.

Then I built the production planning system:

  • Producing while knowing where to store. Since pickup slots were booked three months ahead, the system knew what had to be produced. When production was recorded, it suggested the quadrant with available space that would let the customer pick it up fastest on their slot.
  • Stock per quadrant and per row. If a quadrant held four rows of joists and a customer took one, that row was deducted and the quadrant stayed occupied with the other three; once empty, it was freed.
  • Loading plan. When each truck arrived for its slot, the system gave the operator a plan stating which quadrant to pick each product from and in what order.

Results

  • Truck waiting time dropped to zero: trucks arriving during their slot were served right away.
  • Shorter loading time inside the plant, because goods were already stored in the most convenient quadrants.